What is a Construction Loan Draw?

A construction loan draw is a disbursement of funds from the lender to the borrower (or directly to the title company) at specific points during the construction process. Unlike a traditional mortgage where the full loan amount funds at closing, construction loans release capital in stages as work is completed and verified.

This structure protects both the lender and the borrower. The lender confirms that construction is progressing on schedule and on budget before releasing additional funds. The borrower only pays interest on the amount that has actually been drawn, keeping carrying costs lower during the build.

How the Draw Schedule Works

At loan closing, the lender and borrower agree on a draw schedule tied to the approved construction budget. Each draw corresponds to a specific phase or milestone of the build. The budget is broken into line items (foundation, framing, roofing, plumbing, electrical, finishes, etc.), and draws are requested as those phases are completed.

Most construction lenders use one of two draw structures:

Common Draw Milestones

While every project is different, a typical single-family new construction loan will have 4 to 6 draws aligned with these major phases:

1

Foundation

Site work, grading, footings, and foundation poured and cured. Typically 15-20% of the construction budget.

2

Framing

Structural framing complete, sheathing installed, and the building is "in the dry." Usually the largest single draw at 25-30%.

3

Dry-In / Roofing

Roof installed, windows and exterior doors set, building is weathertight. Roughly 10-15% of the budget.

4

MEP Rough-In

Mechanical, electrical, and plumbing rough-in complete. Insulation installed. Approximately 15-20%.

5

Interior Finishes

Drywall, trim, cabinets, countertops, flooring, paint, and fixtures installed. Around 15-20%.

6

Final / CO

Punch list complete, final inspections passed, Certificate of Occupancy issued. Final 5-10% released.

The Draw Request Process

When a milestone is complete and you are ready to request funds, the process typically follows these steps:

  1. Submit the draw request. The borrower (or their general contractor) submits a draw request through the lender's asset management portal. This includes the draw amount, the line items being drawn against, and supporting documentation.
  2. Provide documentation. Most lenders require photos of completed work, lien waivers from subcontractors and suppliers, and an updated budget showing costs incurred to date. Clean documentation speeds up the process significantly.
  3. Third-party inspection. The lender orders an inspection (typically performed by a licensed inspector or appraiser) to verify that the work described in the draw request has been completed. Inspections are usually completed within 2 to 5 business days.
  4. Approval and funding. Once the inspection confirms the work is complete and the documentation is in order, the lender approves the draw and wires the funds. At Ledger, draws fund within 48 hours of approval.

Interest on Drawn Balances

One of the key advantages of a construction loan's draw structure is that you only pay interest on the amount that has been disbursed, not the full loan commitment. If your total loan is $500,000 and you have drawn $200,000, you are paying interest on $200,000.

This is why construction loans are structured as interest-only during the build period. Monthly payments start low and increase as more capital is drawn. Builders should factor this escalating carrying cost into their project pro forma.

Holdback Explained

Most construction lenders retain a holdback (also called retainage) on each draw. This means the lender funds slightly less than 100% of each draw request, holding back a small percentage (typically 5-10%) until the project is fully complete.

The holdback serves as a buffer to ensure there are sufficient funds to complete the project and address any punch list items. The retained amount is released with the final draw after the Certificate of Occupancy is issued and all conditions are satisfied.

Pro tip: Budget for the holdback in your cash flow projections. If the lender retains 10% on each draw, you will need to cover that gap out of pocket until the final release. Experienced builders account for this in their project capital stack from day one.

Tips for Smooth Draws

Building Something? Let's Talk Financing.

Our draw process is designed for speed and transparency. See our construction loan programs or estimate your rate.

Estimate Your Rate Construction Loans